Week of 10/17

WEEKLY STATUS SUMMARY

This week, the project will mainly continue the operations detailed below. The Newbury Street on-ramp may be closed some overnights during Turnpike lane closures: we will update the website once any dates are confirmed. Limited noise is expected overnight for fence removal in the eastbound Turnpike, and ongoing material removal and drain installation near the railroad. During days, foundation wall installation and mass excavation are progressing on site and within the Turnpike workzones.

DETAILED LOOK-AHEAD

TURNPIKE & TRAVEL

  • Turnpike Eastbound (inbound): slow-speed (right) lane remains closed from the Allston Viaduct (the Exit 131 interchange) to just past Mass Ave.

    • The Eastbound work zone will be extended further east with metal safety barriers, to just past the Mass Ave tunnel. Installation will begin this weekend with limited noise expected, and will be complete next week. See Overnight Work below for details.

  • Turnpike Westbound (outbound): slow-speed (right) lane is closed from the Prudential Tunnel to just past Beacon St. This extended closure allows safe and continuous set-ups for Parcel 12 and for the neighboring project to the west, called the Fenway Center.

  • Overnight single-lane closures are expected on the Turnpike, requiring closures of the Newbury Street on-ramp. We will post dates on Construction Updates once confirmed by MassDOT.

  • Concrete wall repairs: within the Turnpike workzones in both directions and under the Mass Ave Bridge, we will continue chipping and repairing the concrete wall. Noise is expected. This work will be limited to daytime hours.

  • The second stage of deck support wall construction is underway on the Turnpike. These foundation walls are being built adjacent to the slow-speed lanes in both directions. This week, we will continue pouring pile caps and walls. This phase is on track to be complete in Fall 2021.

  • Please continue to move carefully through the workzones: pay extra attention to your speed, lane markings, traffic signage, barriers, and any police or construction workers you see.

ON SITE

  • Mass excavation throughout the Boylston Street site is ongoing with interior foundations continuing, which includes pouring pile caps to support walls.

  • Installation of electrical fixtures along the I90 Westbound and Eastbound foundation wall will be ongoing this week.

  • Foundation work including walls, drilled mini piles, and pile caps will continue along the Newbury Street parcel.

  • Foundation work adjacent to the railroad requires careful coordination with train schedules, as certain activities are limited to off-peak periods.

  • Drilled foundations are installed between 7:00 a.m. and 10:00 p.m.

OVERNIGHT WORK

Nighttime work will continue in the highway, along the railway, and within the Boylston Street site along the railroad tracks where required for safety and logistical reasons. The project is taking all appropriate steps to avoid and mitigate noise from demolition. Upcoming overnight work includes:

  • Eastbound workzone extension: barriers will be installed starting Friday 10/22 into next week. Installation must take place overnight, and limited noise is expected.

  • Fence removal along the Eastbound slow-speed fixed workzone will continue this week, with minimal noise expected.

  • Permanent barrier install along Eastbound and Westbound foundation walls within the slow-speed workzones will begin this week, with minimal noise expected.

  • We will continue installing an underground drain adjacent to the railway throughout this week, with some noise expected. This work has to occur overnight in accordance with rail operating restrictions. We will minimize noise as much as possible, including white-noise back-up alarms on equipment. When work is active near the railway, due to national train safety protocols, airhorns will be used to alert workers when trains are passing.

  • Removal of material and loading of the workzone will continue overnight within the Turnpike workzones, both eastbound and westbound. This work requires travel lane closures that cannot occur during the day. While removing material, the contractor will place sand in the bottom of the trucks to dampen metal noises and will move pieces slowly into the trucks to limit noise.

  • Loading and unloading of the construction zone at the Newbury on-ramp will continue overnight and in the early morning to support the ongoing foundation activities.

Always check the Construction Updates page for the latest information and scheduled activities. Workhours are coordinated with MassDOT and with MBTA and are subject to change based on weather.

OTHER NEARBY WORK

  • Verizon is doing daytime utility work in the left lane of Newbury Street approaching the I-90 on-ramp. Access to the ramp is maintained while this work is going on, though it may appear blocked when approaching from Mass Ave. Any closure should include posted detour signage.

Construction and maintenance work unrelated to this project continues in the area. This includes local utility and street work, rehabilitation of portions of the Mass. Ave. Bridge, other construction projects along I-90 and in the neighborhood, and routine road maintenance. These other construction activities may have noise and/or traffic impacts that are not covered in these BuildP12 project updates. We will strive to provide information about these as a courtesy wherever possible.