PROJECT STATUS SUMMARY
The project will continue the operations detailed below, with minimal overnight noise impacts expected. Wall installation and mass excavation are progressing. No noisy overnight activities are anticipated for next week.
DETAILED LOOK-AHEAD
TURNPIKE & TRAVEL
Turnpike Eastbound (inbound): slow-speed (right) lane remains closed from the Allston Viaduct (the Exit 131 interchange) to just past Mass Ave.
Turnpike Westbound (outbound): slow-speed (right) lane is closed from the Prudential Tunnel to just past Beacon St. This extended closure allows safe and continuous set-ups for Parcel 12 and for the neighboring project to the west, called the Fenway Center.
Within the Westbound Turnpike workzone and under the Mass Ave Bridge, we will continue chipping and repairing the concrete wall. Noise is expected. This work will be limited to daytime hours.
The second stage of deck support wall construction is underway on the Turnpike. These foundation walls are being built adjacent to the slow-speed lanes in both directions. This week, we will continue pouring pile caps and walls. This phase is on track to be complete in Fall 2021.
Please continue to move carefully through the workzones: pay extra attention to your speed, lane markings, traffic signage, barriers, and any police or construction workers you see.
ON SITE
Mass excavation throughout the Boylston Street site is ongoing.
Excavation and foundation work including drilled mini piles and pile caps will continue along the Newbury Street parcel.
Foundation work adjacent to the railroad requires careful coordination with train schedules, as certain activities are limited to off-peak periods.
Drilled foundations are installed between 7:00 a.m. and 10:00 p.m.
OVERNIGHT WORK
Nighttime work will continue in the highway, along the railway, and within the Boylston Street site along the railroad tracks where required for safety and logistical reasons. The project is taking all appropriate steps to avoid and mitigate noise from demolition. Upcoming overnight work includes:
Removal of material and loading of the work zone will continue overnight within the Turnpike work zones, both eastbound and westbound. This work requires travel lane closures that cannot occur during the day. While removing material, the contractor will place sand in the bottom of the trucks to dampen metal noises and will move pieces slowly into the trucks to limit noise.
Loading and unloading of the construction zone at the Newbury on-ramp will continue overnight and in the early morning to support the ongoing foundation activities.
On Thursday night 9/16, we will need to access the Eastbound slow-speed workzone, requiring us to shift the removable barriers. This will create some noise, and we will approach this activity carefully to minimize any disturbance.
Always check the Construction Updates page for the latest information and scheduled activities. Workhours are coordinated with MassDOT and with MBTA and are subject to change based on weather.
OTHER NEARBY WORK
Construction and maintenance work unrelated to this project continues in the area. This includes local utility and street work, rehabilitation of portions of the Mass. Ave. Bridge, other construction projects along I-90 and in the neighborhood, and routine road maintenance. These other construction activities may have noise and/or traffic impacts that are not covered in these BuildP12 project updates. We will strive to provide information about these as a courtesy wherever possible.