Turnpike and Rail
No impacts in the next two weeks.
On Site
General site preparations and clearing
Initial foundation preparations, including soil excavation
Initial utility work within the site
Surveying overnight Thursday on the Newbury St on-ramp
Work Hours
Typical work hours will be Monday - Friday, 7:00 a.m. to 5:00 p.m. No weekend work is anticipated during these two weeks. The Newbury St on-ramp will be closed overnight on Thursday 8/6 from 11:00 p.m. - 5:00 a.m. with detours and signage in place.
Completed Work
Over the last two weeks, we have been focused on initial construction activities to secure and clear the site: installing barriers along Boylston and Newbury Streets, removing the existing Boylston Street lot to provide access to the foundation work areas, removing parking meters on Boylston Street, and replacing light poles with temporary lighting on pedestrian paths.